Project profile

Project: Rushere-Nshwerenkye Road (11.1km ),

Funder: GOU

Surfacing: DBST

Contractor: CHICO

Supervision Consultant::UNRA in-house

Works Contract: UGX 27.704 bn

Project performance

Works commenced on 15th April 2017 and scheduled to be completed on 13th April 2018.

By end of March 2019, 100% of the physical works were complete against the planned 100% (based on the Contractor’s work plan). Time elapsed is 100%

The financial progress stands at 98.7% against the planned 100%

 

Land and property compensated

  • Total amount approved: 893,163,570/=
  • Total amount paid: 730,453,880/=
  • Total Amount Pending: 162,709,690/=
  • Total no of PAPs: 57 PAPs
  • Total no of PAPs paid: 38 PAPs
  • %ge of Paps paid: 66.67%
  • Total PAPs Pending: 19 PAPs
  • Total land captured: 7.395 Acres
  • Total land acquired:5.576 Acres
  • %ge of land acquired: 75.4%