Project profile

Project: Rukungiri-Kihihi-Ishasha/Kanungu (78.5 km)

Funder: ADB/GOU

Surfacing: DBST

Contractor: China Henan International Construction Company

Consultant: SMEC International Pty

Works Contract: UGX; 207,834,646,967

Supervision contract: USD 4,712,121.76  UGX 12,478,542

Project progress

The contract for civil works was signed on 17th September 2018.

Commencement was issued for 5 November 2018 and Contractor is mobilizing Equipment and setting up the main camp in Kihihi.

The cumulative Physical progress as of April 2019 was 1.22% of works out of the programmed 1.1%. Time progress is 13.9%.

Land and Property compensation

  • Total Amount Approved: 21,370,318,450/=
  • Total Amount Paid 18,983,538,174/=
  • Total Amount Pending: 2,386,780,276/=
  • Total PAPs Valued: 2234
  • Total PAPs paid: 1959
  • %ge of paps paid: 87.69%
  • Total PAPs Pending:275
  • Total Land Captured: 220.414 acres
  • Total Land Acquired: 179.94 acres
  • %ge of paps paid: 81.64%
  • Total Land Pending:40.474 acres
  • Total Km Covered: 42 km paid & 6 km pending payment.
  • Supplementary Report has been submitted to CGV.

 

Section 2(Nyakasharara – Ishasha 32.3Km)

  • 1069 PAPs out of 1167 PAPs were verified.