Project Information

Project Name: Rehabilitation of Fort Portal – Hima Road

Length: 55km

Funder(s): GOU

Contractor: China Wu Yi Co. Ltd

Contract Amount: UGX94Bn

Supervision Consultant: SABA ENGINEERING PLC Ltd

Contract Amount: UGX 4.0Bn

Expected Works Completion Date: 25 September, 2019

 

Progress / Status: Works commenced on 26 March, 2018 and scheduled to be complete by 25 September, 2019.

8.00% of the works were complete by end of April 2019 against the plan of 56.51%. Time progress stands at 75.4%. Financial progress is at 14.23% against 59.24%. Contractor has submitted a claim for EOT arising from delayed issuance of detailed designs. Employer to offer their determination.

 

Challenges:

Slippage is majorly due to Late issuance of designs and late mobilization of the Contractor.

 

Land Acquisition Information

Project Affected Persons (PAPs) Compensation

Total Number of PAPs: N/A

Total Compensation Amount Approved: N/A

Total Amount Paid: N/A

Total Amount Pending: N/A

Percentage of PAPs Paid: N/A

Number of PAPs: N/A

PAPs paid: N/A

Add Comment

Top