Project Profile

Project: Pallisa-Kamonkoli (44Km)

Funder: IDB/GoU,

Surfacing: AC,

Contractor: The Arab Contractors

Supervision Consultant: Still Under Procurement

Works Contract: UGX 205.513 Bn,

Project Progress

Commencement was issued on 15 June 2018. Cumulative physical progress by end of April 2019 was 9.25% against 9.05% planned. Time elapsed is 34.94%.

The financial progress stands at 17.37% against the planned 19.01%

 

Land and Property Compensation PALLISA-YOYO( 20.14KM)

Total amount approved: 11,950,717,999/=

Total amount paid: 10,422,604,450/=

Total no of PAPs: 1,143

Total No. of PAPs paid:1010

%ge of paps paid: 88.36%

Total PAPs unpaid: 142

Total Amount Pending:1,528,113,549/=

Total Land Size: 211.329 acres

Total land acquired: 177.758 acres