Project Profile

Project: Mubende – Kakumiro – Kagadi road (107km),

Funder: GOU,

Surfacing: Asphalt Concrete

Contractor: China Communications Construction Company (CCCC) Ltd

Consultant: AIC Progetti SPA with Prome Consultants Ltd

Works contract: UGX 484.887 Bn

Supervision contract: UGX 4.4 Bn, USD 266,000, Euro: 1.71m

Project progress

The contract for civil works commenced in February 2016 and was scheduled to be completed in February 2019. EoT of 287 was granted, Revised completion date is 23rd January 2020.

The cumulative Physical progress as of April 2019 was 58.45% of works out of the programmed 69.79%.

The cumulative Financial Progress was 52.07% out of planned 67.48%.   Time elapsed is 79.22%.

Land and Property compensation

  • Total amount approved. 20,320,345,213/=
  • Total Amount Paid: 15,789,621,712/=
  • Amount not Submitted:4,530,723,501/=
  • Total number of PAPs: 2219
  • Total number of PAPs paid: 2045
  • %ge of paps paid: 92.16%
  • Total PAPs not Submitted:174
  • Total Land captured: 768 Acres
  • Total Land acquired: 503 Acres
  • Total Land not Submitted:265 Acres

 

Addendum Report

  • Total amount approved. 440,022,102/=
  • Total Amount Paid: 402,132,597/=
  • Amount Pending: 37,889,505/=
  • Total number of PAPs. 60
  • Total number of PAPs paid. 42
  • %ge of paps paid: 70%
  • Total PAPs Pending:18
  • Total Land captured: 257 Acres
  • Total Land acquired: 247 Acres
  • %ge of land acquired: 99.84%
  • Total Land Pending: 010 Acres