Project Information

Project Name: Mbarara Bypass

Length: 41Km

Funder(s): EIB

Contractor: China Railway Seven Group Co., ltd

Contract Amount: Euros 58.714m

Duration:

Supervision Consultant: COWI

Contract Amount:

Expected Works Completion Date: Provisional completion 17 December 2017

 

Progress / Status: Commenced in November 2013 and addendum No.01 signed for widening the Bypass to a dual carriageway on 30 September 2016. Addendum 02 for upgrading of a 0.9km access road from the Bypass to Ruti trading Center was signed on 16 June 2017. Works were provisionally completed 17 December 2017.

Remarks: The final inspection was carried out during March 2019 and it was found that the Contractor had rectified all defects. What remained was submission of approval of the Final Environmental Mitigation Report by NEMA before issuance of the Final Account and Final Acceptance Certificate

 

Land Acquisition Information

Project Affected Persons (PAPs) Compensation

Total Number of PAPs:

Total Compensation Amount Approved: 23,343,584,726/=

Total Amount Paid: 19,178,682,661/=

Total Amount Pending: 4,164,902,065

Percentage of PAPs Paid: 90%

Number of PAPs: 108

PAPs paid: N/A

Percentage of PAPs paid: 90%

Percentage of PAPs Unpaid: 10%

PAPs pending: N/A

 

Land Acquisition

Total Land Required: 380.027 acres

Total Land Acquired: 172.918 acres

Total Land Pending: 207.109 acres