Project profile
Project: Kyenjojo – Kabwoya (100 km),
Funder: IDA/GoU,
Surfacing: DBST
Contractor: Shengli Engineering Construction (Group) Co Ltd of Shengli Oilfield
Consultant: Comptran Engineering & Planning Associates (Ghana)
RAP Consultant: Survey Consult Ltd
Works contract: UGX 214.564 BN
Supervision contract: USD 3,079,482
RAP Contract: UGX 1.08 Bn,
Project Progress
The contract for civil works commenced on 5th April 2016 and scheduled to be completed on 4th April 2019.
The cumulative progress as of April 2019 was 59.64% of works out of the programmed 83.59% (in relation to the revised programme 2). Time elapsed is 86.37% as per the revised contract duration of 41.6 months
Land and Property Compensation

Total amount Approved: 24,596,602,629/=
Total Amount Paid: 22,441,496,550/=
Total Amount Pending: 1,463,956,28/=
Total no of PAPs paid: 5721 PAPS
Total Land captured: 591.10acres
Total Land Acquired: 578.3acres
Total Land Pending:12.87acres