Project Profile

Project: Kitala-Gerenge (10KM) ,

Funder: GOU,

Surfacing: Asphalt

Contractor: In-house Construction Team

Supervision: In House Supervision Team under DNPE

RAP Consultant: In-house Land Acquisition Team

Works Budget: UGX 21Bn

Supervision Budget: 450million

RAP Contract: 25bn,

 

Project Progress

Physical Works Commenced on 23rd July 2018 with Bush clearing.

Physical progress as at the end of April 2019 panned 23.86% with a time progress of 50.85%

 

Land and Property Compensation

Total Value: 30,584,168,207 /=

Amount paid: 19132150144/=

Number of PAPs: 1115

PAPs paid: 854

Percentage of paps paid: 76.59%

Total Land: 90.605 Acres

Land Acquired: 49.863 Acres

%ge of land acquired: 55.03%