Project Profile

Project: Kigumba Bulima (69Km)

Funder: ADF, DFID and GOU,

Surfacing: Asphalt Concrete

Contractor: China Railway No 5 Engineering Group Co. Ltd

Supervision: Gauf Engineers in Association with Gauf Consultants Uganda

Works Contract: UGX 159,608,817,498

Supervision Budget: Euros 1,477,305 and UGX 1,665,078,940

 

Project Progress

The project commenced on 1st March 2018 and is scheduled to be complete on 16 August 2020. The physical works started on 6th June 2018.

By end of April 2019, 18.5% of the physical works had been completed against the planned 38%. Time elapsed is 47%

 

Land and Property Compensation

Supplementary Report I and II (25km)

Total amount approved –UGX 8,589,431,604/=

Total Amount paid –UGX 6,555,756,730/=

Total Amount Pending – UGX 2,033,674,874/=

Total number of PAPs –1,182

Total number of PAPs paid –1,030

%ge of paps paid: 87.14%

Total PAPs pending –156

Total land captured – 127.44 acres

Total land acquired–98.14 acres

%ge of land acquired: 77%

Total land pending–29.30 acres

Total Km acquired –25km (as site the contractor can access)

 

Supplementary Report III (14km)

Total amount approved –UGX 2,125,838,032/=

Total Amount paid –UGX 922,125,914/=

Total Amount Pending – UGX1,203,712,118/=

Total number of PAPs –502

Total number of PAPs paid –299

%ge of paps paid: 59.56%

Total PAPs Pending –203

Total land captured –68.99 acres

Total land acquired–39.90 acres

Total land pending–29.09 acres

%ge of land acquired: 56.52%

Total Km acquired –13km (as site the contractor can access)

 

Supplementary Report IV (30km)

Total amount approved –UGX 9,429,726,254/=

Total Amount paid –NIL

Total number of PAPs –1,067

Total number of PAPs paid –NIL

Total land captured – 167.58 acres

Total Km acquired –NIL