Length: Kashenyi – Mitooma: 11.53Km and Kitabi Seminary Access Road: 0.8Km

Funder(s): GOU

Surfacing: Asphalt

Contractor: Chongqing International Construction Corporation (CICO). Contract Amount: UGX 49.199 bn Duration: 1 year

Supervision Consultant: International Ltd with KOM Consult, UNRA In-house Supervision (Since April 2018). Contract Amount: UGX 4,634,915820

RAP (Resettlement Action Plan) Consultant: In-house.  Contract Amount: UGX 7Bn

Expected Works Completion Date: 31 January 2018

Progress / Status: Cumulative progress by end of April 2019 was 100% against a plan of 100%. Contract time elapsed was 100% and takeoff certificate was issued. The project is now under defects liability period

Remarks: The project started on 31 January 2017 and scheduled to be complete by 31 January 2018. New revised completion date is 16th January 2018 and works were complete by this date. Financial Progress is at 97% against the planned 100%.

PAPs (Project Affected Persons) Compensation

Original Report

Total Number of PAPs: 802

Total Compensation Amount Approved: UGX 13,328,539,162

Percentage of PAPs Paid: 92.76%

Supplementary Report

Total Number of PAPs: 164

Total Compensation Amount Approved: UGX 4,423,788,472

Percentage of PAPs Paid: 86%

Land Acquisition

Original Report

Total Land Required: 77.046 acres

Total Land Acquired: 62.624 acres 

Supplementary Report

Total Land Required: 14.582 acres

Total Land Acquired: 11.799 acres