Project Profile
Project: Kampala Northern Bypass (17.5km) ,
Funder: EU/EIB/ GOU,
Surfacing: Asphalt ,
Contractor: Mota Engil Enginharia E Contrucao SA
Supervision Consultant : COWI A/S
Works contract: Euros 67.934 m Revised to Euros 106.48 m
Supervision contract: Euros 3.431m Revised to Euros 6.829 m,
Project Progress
The Contractor commenced civil works on 14 July 2014 and scheduled to be complete in July 2017. An Extension of Time (EoT) of 337 days was awarded with a revised completion date of 29 May 2019 for both the Contractor and the Supervisor’s Representative.
The cumulative progress by end of April 2019 was 58.1% against the programmed 59.1% based on the revised program with a completion of 15 August 2022. Time elapsed is 58.3 % as per the revised completion date of 15 August 2022. Financial Progress stands at 58.5% against the planned 58.1%
Issues
There has been increase in scope of works due to omissions and drainage review. The revised project cost is Euro 106,489,753.07
Delayed Access to Site due to design improvements, disputed compensated amounts by PAPs, family disputes over land ownership. ,
Land and Property Compensation
Total Amount Approved: 83,863,652,923/=
Total Amount Paid: 69,347,488,188/=
Total Amount Pending: 14,516,164,735/=
Total PAPs Valued: 1,581
Total PAPs paid: 1160
%ge of paps paid: 73.37%
Total PAPs Pending:421
Total Land Captured: 59.900 acres
Total Land Acquired: 48.05 acres
%ge of land acquired: 80.22%
Total Land Pending: 11.85 acres