Project Information

Project Name: Jinja/Kamuli Town Roads

Length: 22Km

Funder(s): GOU

Contractor: CICO

Contract Amount: UGX 40.918Bn

Duration:

Supervision Consultant: In-house supervision

Contract Amount: N/A

Expected Works Completion Date: N/A

 

Progress / Status: Construction commenced on 27 June 2016 and scheduled to end 26 December 2017. However, the project was extended to 1st March 2018. By end of March 2019, all the works were complete and under Defects Liability Period.

Remarks:

 

 

Land Acquisition Information

Project Road: Wakitaka-Bugembe Road
Length:
3km

 

Project Affected Persons (PAPs) Compensation

Total Value Approved: 976,639,934/=

Total Amount paid: 893,162,313/=

Amount Pending: 83,477,621/=

Number of PAPs: 179 PAPs

PAPs paid: 175 PAPs

Percentage of PAPs paid: 97.77%

PAPs pending: 4 PAPs

 

 

Land Acquisition

Total Land Required: 10.23 acres

Total Land Acquired: 10.107 acres

Percentage of land acquired: 97.65%

Land Pending: 0.243 Acres

Total Km Covered: 3km