Project profile

Project: Akisim-Moroto Road (50.3Km)

Funder: GOU,

Surfacing:

Contractor: CR No.3

Supervision Consultant: COWI A/S

Works Contract:UGX 248,069,399,125.90

Supervision Contract: 13,070,799,800

Project progress

Works commenced in November 2016 and scheduled to be completed on 30th   April 2019. The project duration is 30 months.

The cumulative progress as of April 2019 was 95.04% of works out of the programmed 97.04%. Financial progress stands at 91.17% against 96.67% planned Time elapsed is 96.67%.

Land and property compensation

Total amount approved: 4,082,978,007/=

Total amount paid: 2,773,789159/=

Total amount Pending: 1,429,622,362/=

Total no of PAPs: 1199

Total no of PAPs paid: 974

%ge of paps paid: 81.23%

Total PAPs Pending: 254

Total land captured: 495.633 Acres

Total land acquired: 328.06 Acres

%ge of land acquired: 66.19%

Total Land Pending: 186.328 Acres