Project Profile
Project:Bulima – Kabwoya (66 km)
Funder: AfDB/DFID/GoU
Surfacing: DBST
Contractor: China Railway No. 5 Engineering Group Co. Ltd (China)
Consultant: Comptran Engineering & Planning Associates (Ghana)
RAP Consultant: Stanfield Property Partners Ltd
Works contract: UGX 141,941,840,327 Revised to UGX 158.914 bn
Supervision contract: USD 1,617,255 and UGX 420,523,062
RAP Contract: UGX 558 million
Project progress
The contract for civil works commenced in December 2015 and scheduled to be completed in May 2018. Following a 6 months EOT due to increased scope of works and 5.5 months EOT due to rainfall, the project is scheduled to be completed on 15th May 2019.
The cumulative progress as of end of April 2019 is 78.75% of works against 93.14%. Time elapsed is 91.5% (As per revised work program No.3). Financial Progress stands at 71.07% against 97%
Land and Property Compensation
Total amount approved:13,053,888,547/=
Total amount paid:8,895,889,544/=
Total Amount Pending: 4,157,999,003/=
Total no of PAPs:2820
Total no of PAPs paid:2381
Total PAPs Pending:439
Total land captured:417.55 acres
Total land acquired:271.856acres
Total Land Pending:145.694 acres
Total Km Covered:66km
12
Project profile
Project: Kyenjojo – Kabwoya (100 km),
Funder: IDA/GoU,
Surfacing: DBST
Contractor: Shengli Engineering Construction (Group) Co Ltd of Shengli Oilfield
Consultant: Comptran Engineering & Planning Associates (Ghana)
RAP Consultant: Survey Consult Ltd
Works contract: UGX 214.564 BN
Supervision contract: USD 3,079,482
RAP Contract: UGX 1.08 Bn,
Project Progress
The contract for civil works commenced on 5th April 2016 and scheduled to be completed on 4th April 2019.
The cumulative progress as of April 2019 was 59.64% of works out of the programmed 83.59% (in relation to the revised programme 2). Time elapsed is 86.37% as per the revised contract duration of 41.6 months
Land and Property Compensation

Total amount Approved: 24,596,602,629/=
Total Amount Paid: 22,441,496,550/=
Total Amount Pending: 1,463,956,28/=
Total no of PAPs paid: 5721 PAPS
Total Land captured: 591.10acres
Total Land Acquired: 578.3acres
Total Land Pending:12.87acres